Sunday 13 May 2012

Tree Planting – Jubilee Day – Tuesday 5th June



Work is presently underway to plant 60 sweet chestnut trees along what is presently known as King George VI Avenue in the arboretum. The walk will then be known as “Jubilee Walk” to commemorate the diamond jubilee of HM The Queen.
On Jubilee Day, Tuesday 5th June 2012, at 10:30 am, the final 2 trees will be planted in a special “topping off” ceremony organised by Walsall Volunteer Tree Wardens and sponsored by The Rotary Club of Walsall.

After the ceremony refreshments, supplied by the Inner Wheel Club of Walsall, will be available at nominal cost.
King George VI Avenue is most easily accessed by the entrance to the Arboretum situated off Sutton Road/ The Crescent, where car parking is available.

All are welcome to attend!!

Tree planting in progress

Friday 11 May 2012

Gallery Garden - Update

The Gallery Garden is well on the way to completion. Hopefully, it will be officially opened by the Mayor of Walsall at 12 noon on June 20th. Photographs below show Marc Read putting the finishing touches to the plinth on which 3-dimensional exhibits will be placed.
Jack Moody's workmen are shown doing floral planting alongside members of the Arboretum User Group.





Wednesday 9 May 2012

Works Progress In The Arboretum - Update

The third phase of work on the Restoration programme which included the refurbishment of the park’s historic Bandstand and Boathouse, conversion of the former lakeside cafe to a shelter and the refurbishment of the former lido cafeteria to a Clubhouse for the Ladies Bowls Team was completed in April 2012.   The Boathouse will be used to support sailing and canoeing activities to be delivered on Hatherton Lake by Walsall Council’s Outdoor Pursuit’s Team (transfer to the Arboretum to take place once the Visitor Centre is completed) and the bandstand will be available for hire during the summer period.

Phase four of the programme – the landscaping of the entire historic core of the park is nearing completion with the majority of work scheduled to be delivered by the end June 2012.  Work completed so far has included:- Footpath repair and resurfacing and creation of new footpaths, repair of historic boundary walls and brook course bridges, entrance improvements, extensive planting and landscaping of ‘redundant’ areas of the park to bring them back into use (old Nursery site adjacent to the Park Tavern and old tennis courts of Arboretum Road), refurbishment of the park tennis courts and creation of new decking platforms on Hatherton Lake and Deep Pond.  During May, new bins and benches will be installed across the site.  We would like to thank park users for their patience as the work programme is being delivered and hope that the improvements to the park are appreciated as the summer period approaches. The final phase of work – the building of a park visitor centre is due to commence in 2013.

Louise Harris - Project Manager